Current Major Capital Projects Information
Two current major capital projects as further described below (major projects greater than $4 million)
Note: BOG has raised amount of major capital projects amount to >$4mil (for reporting purposes)
Project Title: Building 234 Athletic Training Center Addition
(Darrell Gooden Center / University Park)
Project Type: New Construction (Mixed Use Occupancy)
Project Budget: $4,500,000
Funding Source(s):
CITF FY 20-21: $1,224,315
CITF FY 21-22: $775,685
UWF Athletics Foundation: $2,500,000
Construction Type: Construction Manager @ Risk
Architect/Engineer: Goodwyn Mills & Cawood (GMC)
Construction Manager: TBD
Design Start: programming underway
Construction Start: TBD
Substantial Completion: TBD
Construction Percent Complete: 0%
Square Footage: 10,000 gsf (targeted area, includes potential shell space)
(2 levels: 1st Floor - Athletics; 2nd Floor - anticipate FSU COM suite & support services)
Design/Construction Current Status (look ahead of upcoming/ongoing work):
- Following firm reviews with the Athletics Department, proposal scope negotiations with a continuing contract A/E firm for Design Services began in May 2021; with Finalized A/E Proposal with incorporation of all requested scope received 9/2/21. Issuance of Purchase Order for contracted for A/E Design Services September 2021.
- Receipt of FY21-22 CITF funding appropriation in Fall.
- Design Team in process of holding programming meetings with the user groups and developing concept plan layouts.
- Next Milestone – Issuance of QBS Solicitation for Construction Management Services anticipated in 2022; followed by completion of evaluation and selection process; and then contract negotiations and issuance of Purchase Order / contract to Construction Manager.
Project Title: Building 54, Fire Mitigation
Project Type: Renovation
Project Budget: $6,250,000 state appropriation; $7,350,000 overall
Funding Source(s):
PECO FY 21-22: $6,250,000
Additional Athletics / Institutional Funding: $1,100,000 (pending; ref. also note at bottom)
Construction Type: Design/Build
Design / Build Team: Greenhut Construction Co., Inc.; with Caldwell Associates Architects
Design Start: TBD
Construction Start: TBD
Substantial Completion: TBD (projected completion by Summer 2023)
Construction Percent Complete: 0%
Square Footage: 72,921 gsf (existing) / 45,920 nasf (existing)
Design/Construction Current Status (look ahead of upcoming/ongoing work):
- QBS Solicitation for Design/Build Services: the evaluation and selection process was completed October 2021.
- Appropriation allocation for FY22 received Fall 2021.
- Project Kickoff Team Meeting held 11/10/2021.
- Contract negotiations completed (12/2/21).
- Next Milestone – Execution of Contract will follow; with issuance of Purchase Order for the initial pre-construction/design services. Finalization of total contract amount to follow receipt of GMP after design and pricing.
Note: There is also an additional separate HVAC project that will be occurring in Building 54. Cost of this project is budgeted at $900,000 total. Planned scope of this B54 Phase III HVAC work includes replacement of the remaining equipment serving rooms located on the south/southeast sides of the building.